NEC 300.15 · Homes and commercial

When a junction box is required

With conduit and cable wiring, every outlet, switch, splice, junction, termination, wiring method transition and pull point needs a box or conduit body, unless a specific exception in the code allows something else.

Diagram of a framed wall with boxes at switch, splice, outlet and cable-to-conduit points, a conduit body pull point, and a hidden splice marked not allowed.
Every splice, device and change of wiring method lands in a box or conduit body; a taped splice buried in the framing is not one of the allowances. Diagram: Farmer Works Electric, free to share under CC BY 4.0 · Download PNG · How to credit

What the code requires

For conduit, tubing, and cable wiring methods such as AC, MC, MI and NM cable, the code requires a box or conduit body at each outlet point, switch point, splice point, junction point, termination point, wiring method transition point and pull point, unless one of the specific allowances in 300.15(A) through (L) applies.

Fittings and connectors may be used only with the wiring methods they are designed and listed for. Concealed knob-and-tube wiring needs a box at every outlet and switch point.

On the job

  • Splices buried in a wall or ceiling with no box are a common correction.
  • Unless one of the specific allowances applies, a splice point needs a box or conduit body, so a splice cannot simply be taped and hidden in the framing.
Pile of red and yellow twist-on wire connectors
Twist-on wire connectors (representative stock photo).

Exceptions that matter

  • An identified fitting may be used instead of a box where the conductors are not spliced or terminated in it. It must stay accessible unless it is listed for concealment.
  • Direct-buried conductors and cables do not need a box at splices and taps made under 300.5(E).

What changed in 2023

The 2023 edition added wiring method transition points, such as where one cable or raceway type changes to another, to the list of places that need a box or conduit body.

Related sections

Where this comes from

0/300

Answers come from this library only and are written by AI. They can be wrong, so check the cited section and confirm with your building department.

San Clemente · South OC to North County San Diego

Send a photo. Get a real answer.

Text is fastest, and a photo quote is free. Call if it is urgent, if you smell something burning, or if a breaker will not reset.

Electrical work contracted under C K ELECTRIC · CSLB Lic. #354550 (C-10) · Farmer Works Electric license in process