NEC 250.24 · Homes and commercial

Grounding and bonding at the service

At the service, the neutral connects to the grounding electrode system, and each service disconnect enclosure needs a main bonding jumper. No neutral-to-ground connection is made on the load side, except where Article 250 specifically allows it.

Wiring diagram: neutral bonded to ground at the service by the main bonding jumper, GEC to a ground rod, neutral isolated in the subpanel.
The 2023 code relettered this section: the load-side ban is now (B), the main bonding jumper (C) and the neutral (D), so older checklists may cite different letters. Diagram: Farmer Works Electric, free to share under CC BY 4.0 · Download PNG · How to credit

What the code requires

The grounding electrode conductor (GEC) connects to the service neutral at an accessible point between the load end of the service drop, lateral or service conductors and the neutral terminal at the service disconnect. The meter socket or the disconnect both comply; check the utility's rules. An outdoor transformer needs at least one more neutral-to-electrode connection.

In the 2023 lettering, 250.24(B) prohibits any neutral-to-ground connection on the load side of the service disconnect, 250.24(C) requires a main bonding jumper in each service disconnect enclosure, and 250.24(E) sizes the GEC under 250.66.

Under 250.24(D), the neutral must be run with the phase conductors to each service disconnect, even if there are no line-to-neutral loads. It must be at least the size in Table 250.102(C)(1). Having enough ampacity for the calculated neutral load (220.61) is a separate check under the service conductor rules in 230.42. In parallel runs, the neutral in each raceway must be at least 1/0 AWG. On a 3-wire delta service, its ampacity must be at least that of the phase conductors.

On the job

  • Bonding neutral to ground again in a downstream subpanel, for example by leaving the panel's bonding screw installed, violates the load-side rule in 250.24(B).
  • A missing main bonding jumper in a service disconnect enclosure.
  • An undersized neutral on a parallel service.
  • Plans or checklists using 2020 letters, (B) for the main bonding jumper or (C) for the neutral, are outdated. The 2023 letters are (C) and (D).
Three round electric meters on meter bases with conduit on an exterior block wall
Electric meters on an exterior wall (representative stock photo).

Exceptions that matter

  • A neutral-to-ground connection on the load side is allowed only where Article 250 specifically permits it elsewhere.

What changed in 2023

The 2023 code moved the load-side bonding ban from 250.24(A)(5) to a new 250.24(B), shifting the main bonding jumper to (C), the neutral to (D), the GEC to (E) and ungrounded-system connections to (F).

Related sections

Where this comes from

0/300

Answers come from this library only and are written by AI. They can be wrong, so check the cited section and confirm with your building department.

San Clemente · South OC to North County San Diego

Send a photo. Get a real answer.

Text is fastest, and a photo quote is free. Call if it is urgent, if you smell something burning, or if a breaker will not reset.

Electrical work contracted under C K ELECTRIC · CSLB Lic. #354550 (C-10) · Farmer Works Electric license in process