NEC 230.79 · Homes and commercial

Minimum service size, including 100 A for homes

A service disconnect must be rated for at least the calculated load. The minimums are 100 A for a one-family home, 60 A for most other installations, 30 A for up to two 2-wire circuits, and 15 A for a single branch circuit.

Bar chart of minimum service ratings: 15 A one branch circuit, 30 A two 2-wire circuits, 60 A other installations, 100 A one-family home.
The minimum is a floor: when the Article 220 load calculation comes out higher, the service disconnect has to be rated for the larger number. Diagram: Farmer Works Electric, free to share under CC BY 4.0 · Download PNG · How to credit

What the code requires

The service disconnect's rating must be at least the load calculated under Article 220 (Part III, IV or V), and it can never be below the minimums in 230.79(A) through (D).

The minimums are 15 A for an installation with a single branch circuit; 30 A for no more than two 2-wire branch circuits; 100 A, 3-wire, for a one-family dwelling; and 60 A for all other installations.

The minimum is a floor, not a target. If the load calculation comes out higher, the disconnect must be rated for the larger number.

On the job

  • A new single-family service rated below 100 A is a correction.
  • A service rating that does not cover the Article 220 calculated load is a correction, even if it meets the minimum.
  • Disconnects at detached buildings follow the same minimum ratings under 225.39.
Three round electric meters on meter bases with conduit on an exterior block wall
Electric meters on an exterior wall (representative stock photo).

In California

California does not amend this section. Separately, CEC 706.10 points to Energy Code 150.0(s), which sets battery-storage readiness, including a minimum panelboard busbar rating, for newly built single-family buildings (one or two dwellings) with service over 125 A, unless a battery system is installed.

Related sections

Where this comes from

0/300

Answers come from this library only and are written by AI. They can be wrong, so check the cited section and confirm with your building department.

San Clemente · South OC to North County San Diego

Send a photo. Get a real answer.

Text is fastest, and a photo quote is free. Call if it is urgent, if you smell something burning, or if a breaker will not reset.

Electrical work contracted under C K ELECTRIC · CSLB Lic. #354550 (C-10) · Farmer Works Electric license in process